Sunday, February 28, 2016

Project Launch Process L320

L320 - Review / Reconfirm / Agree Path Plan

SIIMS Project Launch - L.png

DEFINITION

SIIPS Project Launch L320.pngReview, and, if appropriate, revise and agree the high-level management "Path Plan" based on results from the previous segments.  Appropriate level of client sign off will be required.  Equivalent changes may be required in other documentation.

SUMMARY

During the Requirements Segment and again during the Selection Segment, the parameters which affect the remainder of the project may change.  Therefore a review of the current Path Plan should normally be performed.

PATH PLANNING GUIDANCE

This process is normal practice.

DEPENDENCIES

Prerequisites (Finish-Finish):
  • QA Signoff of previous segment (Q180)
  • Reconfirm Approach (L310)
Dependent procedures (Finish-Finish):
  • Confirm or renegotiate KPMG’s contractual relationship (L150)
  • Detail the Segment Plan for the following segment (L120)
  • Detail / revise staffing, team structure and organisation for the following segment (L130)

RECEIVABLES

  • Project Constitution showing terms of reference, scope and objectives
  • Definition of business needs and anticipated benefits
  • current Path Plan
  • Quality Plan showing approach to:
    • project management,
    • change management,
    • use of other methods and techniques,
    • quality review and sign off.
  • Organisation structure of the client organisation
  • Available resources details / skill sets

DELIVERABLES

  • Updated high-level management Path Plan showing high-level timescales, sequencing, dependencies, deliverables, and resources requirements
  • Corresponding updates if appropriate to other key project documentation, for example
    • Project Constitution showing terms of reference, scope and objectives
    • Definition of business needs and anticipated benefits
    • Quality Plan,
    • Project Organigramme

TOOLS

  • ITPM Core Guide
  • Example plans
  • Project planning software
  • Estimating Model software (spreadsheets)

DETAILED DESCRIPTION OF TASKS

In Process L310 the overall approach to the project was reviewed to reconfirm the original approach, or to define a modified approach, based upon the results of the preceding segment.  This may have led to major or minor changes in the selected path for the coming segment of the project.  In this process, the Path Plan is revised accordingly.
All activities carried out when originally defining the Path Plan are re-visited at the end of each segment.  The reason for this is so that a more accurate high level management aide will be available for the rest of the project, based upon the knowledge gathered to date about changes to the project.
This review may need to consider the following topics:
  • the project boundaries,
  • the implementation strategy,
  • client sponsor commitment,
  • the activity plan,
  • high level estimates,
  • the resourcing requirements,
  • the project organisational structure,
  • sub-contractor relationships,
  • the risks and risk management,
  • issue resolution and change control procedures,
  • quality management procedures, and,
  • the reporting structure.
The overall approach and issues are considered in detail in Process L090 - “Produce Path Plan”.  The deliverables are identical to those in L090 except that they are more up to date and only relevant for the remaining segments.  Similar considerations will also apply in terms of review and agreement by the project sponsor, and other key participants.  See Process L090 for full details.

Project Launch Process L310

L310 - Reconfirm Approach

SIIMS Project Launch - L.png

DEFINITION

SIIPS Project Launch L310.pngBetween the work segments, a review is made to ensure that the planned approach to the project remains in the best interests of the client organisation.  Any issues are discussed and agreed with the client at a senior level.

SUMMARY

The outcome of the previous work segment may indicate that a different approach is now preferred.  When the findings have become clear, the overall approach should be reviewed to see whether it remains the best business solution for the client organisation.  The organisation’s needs and business options should be considered to establish the best course of action.  These issues should be discussed and agreed with the project’s sponsor and any other key decision makers within the client organisation.

PATH PLANNING GUIDANCE

This process is normal practice.

DEPENDENCIES

Prerequisites (Finish-Finish):
  • Finalisation of preceding work segment
Dependent procedures (Finish-Finish):
  • L320 Review / reconfirm / agree high-level “Path Plan”
  • Detailed “Segment Launch” of following work segment

RECEIVABLES

  • Project constitution - scope, terms of reference, objectives
  • Definition of business needs and anticipated benefits
  • Findings from preceding work segment

DELIVERABLES

  • Permission to Proceed

TOOLS

  • Path templates and process descriptions

DETAILED DESCRIPTION OF TASKS

The relevant findings and outcomes from the preceding work segment should be presented to the project’s sponsor and other  key decision makers within the client organisation.  It may be appropriate to agree these informally with the sponsor and then to present them formally at a Steering Committee meeting.
The impact of the findings upon the project’s objectives and anticipated benefits should also be presented and reviewed.  It may be useful to demonstrate the impact on the project’s Benefit Model if one has previously been prepared.
Any new or revised options for the business solution should now be identified and considered.  The relative merits of the options should be analysed, discussed and agreed leading to an agreed recommendation concerning the way forward.
Details of the way forward will be expanded into a revised high-level “Path Plan” (if necessary) in Process L320 - Review / reconfirm Path Plan.  Full detail of the plan will be developed during the following Segment Launch processes.

Project Launch Process L200

L200 - Present Project/Segment Approach to User Community and Team

SIIMS Project Launch - L.png

DEFINITION

SIIPS Project Launch L200.pngOrganise formal and informal events to brief all participants (whether or not officially part of the project team).  They will need to understand the client organisation, scope and objectives, methods and approach, infrastructure, and management/control methods etc.

SUMMARY

Before the project really starts its activities, the people involved and affected by it will need to be briefed about the project, its intent, who is involved, which responsibilities they will have and how the project is going to work.
This briefing is the first major communication exercise to the project team and people outside the project team.  As such it will need to address the typical questions surrounding any communication effort:
  • Who needs to be briefed?
    • A distinction will need to be made between people who need to know information so that they can work correctly, and people who need to know for information purposes only.
  • What do they need to be briefed on?
    • Although there will be common information needs, depending on the groups identified, communication may need to be tailored to specific needs.
  • How is it best communicated
    • Some information can be presented in a written format to people, other information will need to be more thoroughly discussed and maybe there is even a need for training sessions on certain elements of the project approach.
  • Who should be involved in delivering the communication?
    • A mix of specialists, sponsors and project team manager / leaders will probably be needed to ensure the messages that are given are correct, complete, pitched at the right people and carry the credibility needed.

PATH PLANNING GUIDANCE

This process is  optional.  It is good practice where there are several people involved in the project.

DEPENDENCIES

Prerequisites (Finish-Finish):
  • Review/confirm ToR, Scope, Objectives (L010)
  • Review/confirm business needs and anticipated benefits (L020)
  • Do quality plan (L080)       
  • Produce Path Plan (L090)
  • Define organisation, people, support requirements (L100)
  • Segment Plan (L120)
  • Agreed project organisation and roles (L130)
  • Mobilise Resources (L160)
  • Set-up/review user involvement (L170)
  • Set-up/review management organisation (L180)
  • Implement/re-implement project management and control techniques (L190)
  • Setup/revise and agree communications plan (L060)
Dependent procedures (Finish-Finish):
  • Following segment processes

RECEIVABLES

  • Project Constitution
  • Definition of business needs and anticipated benefits
  • Path Plan
  • Quality Plan
  • Segment Plan - ie detailed plan for the segment
  • Project Organigramme
  • Communication Plan

DELIVERABLES

  • Project approach presentation meeting
  • Project approach briefing pack

TOOLS

  • (none)

DETAILED DESCRIPTION OF TASKS

The purpose of the presentation of the project approach to the project team and the users is twofold:
  • ensuring that all the people who will be involved in the project know its context, its organisation, principles of working,
  • so that participants can interpret how they fit into that bigger picture,
  • to start building project team and user commitment to the project objectives and approaches.
To ensure these objectives are met successfully, the project manager and project sponsor will need to :
  • identify who needs to know what,
  • take the actions necessary to ensure the right level of understanding and buy-in.

Identifying who needs to know what

At the start of the project, the project and its context will need to be introduced to a number of interest groups. Typical groups that may need to be considered are:
  • project team members
  • user management who will be part of the project structure (e.g. project board members)
  • other users managers
  • users who will be working with the project
  • other users
  • IT department managers and staff
  • other interest groups, e.g. regulators, non-executive directors, auditors, etc.
To identify successfully all the interest groups, an organisational analysis of the company may be called for.  In practice, it may be difficult to list all the people who need initial information and, as briefing sessions take place, additional groups or individuals may be suggested and extra-briefings are planned as new interest groups are identified.
Each of the groups in question will have different information needs.  For instance, project team members will need to know in detail what the roles of the project team members are and how they are going to use project planning / monitoring tools and techniques such as timesheets.  To other groups (e.g. project board members) a high-level understanding of project progress reporting could be enough and in some cases none of it is actually relevant.
It may be appropriate to organise different events for different groups of people.  In larger projects, affecting many people in different ways (and maybe also covering different geographic locations), a complex briefing programme could be called for.
Typical subjects that may be considered for the briefing are:
  • Business drivers and expected business benefits from the project
  • Terms of reference, scope, objectives of the project
  • High-level plan and projected timeframe
  • Principles of the approach: methods, strategies
  • Project organisation: who is who;, roles and responsibilities; and communication
  • User involvement and communication
  • Specific techniques and methodologies
  • Practical issues: location, infrastructure, etc.
Ensuring the right level of understanding and buy-in
After having identified for each group what the exact need to know really is, the right mechanisms for achieving the understanding and commitment will have to be put in place. The following factors may be considered:
  • participative or directive style
  • selecting the right person to brief the groups
  • appropriate mechanisms, approach and tools.
Depending on the chosen change management approach (see Process L050), the mechanisms may vary from highly participative to very directive.  In a more participative approach, communication  and presentation will start before all elements are fully defined and will allow people to influence the outcome, whereas in a more directive approach the elements will be defined by a small group and the rest of the people will be informed of the outcome.  For each project it must be decided which approach is appropriate for what group of people and which events will need to be tailored as a consequence.
Who delivers the briefing will have an influence on its credibility and will ultimately determine whether people will give the right level of attention to the project.
  • The project sponsor should participate in the briefing and be seen to understand and support the project.  In large organisations there might even be a need to cascade the briefing from management layer to management layer and involve sponsors at different levels of the company.
  • The briefing may be an opportunity to introduce the project management team and have a number of people deal with specific specialist areas.  For a large project team, a cascaded approach to the briefing where the project manager briefs the project management team, who in turn brief their subteams.
  • Subject specialists may be the best people to deal with specific areas, e.g. the planning and estimating approach may be best explained by an expert who does not necessarily have a management role in the project.
Finally, consideration needs to be given to the mechanisms used to brief people.  The following options may be considered:
  • written briefing pack
  • presentation
  • one-to-one meetings
  • workshops, conference
  • video
  • item in existing meetings, publications (company awayday e.g.)
  • training sessions
  • manuals
  • project launch celebration or social event.
It is unlikely that one single mechanism will satisfy all the needs for everyone and therefore a number of techniques may be used.  For instance, project team members could attend a conference to obtain a high-level understanding and then go through tailored training programmes to equip them fully for their role on the project, while at the same time, the project sponsor is going round different parts of the organisation with a video based presentation.

Timing the briefing


Briefing the project team and the users is usually not a one-off exercise, but a process that needs to be repeated.  The start of a new segment is a typical milestone which will require some level of briefing.  Especially on longer projects maintaining the project team and user understanding and commitment can be a challenge.  Regular updates on how things have evolved and why will help users and project team members adjust their expectations and maintain their commitment to the project.