Thursday, October 11, 2018

Asset Management for Projects

Purpose

This provides guidelines for the management of project assets and version control procedure. It covers
 the requirements, considerations and steps for the management of project assets and controls.
All projects require that documentation, procedures and files be controlled. Project property includes 
both physical and non-physical materials, this could be a wide variety of items, such as, deliverable 
documentation (hardcopies and files), hardware, structures for LANs (local area networks) and 
personal computers, training materials, and general data files. It is essential to the success of the 
project that particular attention be placed on the management of this function, particularly with the use 
of internet for distribution, which can increase the difficulties of managing simple tasks such as version
control.

Rationale

Asset management is the collective term used for the control of tangible project property — primarily 
project deliverables — throughout the project lifecycle. Asset management encompasses a major 
project management area previously referred to as version control, but includes additional areas of 
control over all project property.
Structured processes within the area now referred to as asset management include controls needed 
to:
  • Ensure that project property (software and documents) is physically secure at all times;
  • Protect the integrity of completed deliverables;
  • Control updates made to completed deliverables;    
  • Ensure that the appropriate version of a deliverable is used;
  • Control the release and issuance of updated deliverables; and,
  • Ensure that related deliverables are kept in step.
Asset management also ties directly into the change control process. It
is essential that this function is implemented as a foundation to support base
lining of project deliverables and the control of project change.

Requirements

At a minimum, the following categories of asset control elements are required for effective asset 
management:

Asset Control Element

Description

Define Scope & Requirements for Project 
Assets
Identifying both deliverable and 
non–deliverable items and their clients, 
then designing an appropriate 
organisational structure to effectively 
administer control and management of 
the identified items. e.g. Hardware is 
anon-deliverable item required by the 
development team
Develop Asset Management Plan
This is the key document produced by the
 asset management owner, outlining 
processes for how asset controls will be 
implemented on the project.i.e. Security 
procedures, project library, filing system 
etc
Implement and Administer Asset Management 
Processes
       
Implementation and ongoing 
administration of the asset managers 
responsibilities. As detailed work in the 
asset management plan.

Asset Management Definition and Scope

This activity involves identifying both deliverable and non–deliverable items and establishing an 
appropriate organisational structure for the project assets to effectively control and manage the 
identified items. In addition, an asset management plan should be developed. This plan should 
include the detailed asset management procedures and specific security processes.
Project deliverables are valuable assets in which the business has invested. If the components 
of deliverables are not controlled, a small change may render them useless.
The first step in implementing effective asset management involves identifying who the “clients” 
of the function are, and documenting their requirements. It also involves defining the scope of 
project deliverables subject to change control and the scope of the asset manager’s 
responsibility.

Asset Management Clients & Requirements

The asset management function will have a number of clients, each with different requirements, 
for example:
  • Development team—need to be able to easily access correct versions of Functional 
    Specification Requirement documents;
  • Quality manager—needs to ensure procedures meet quality requirements, and are 
    being adhered to;
  • Project manager—needs status reporting, particularly on changes (e.g. predicted vs. 
    actual cost of changes). The asset management function needs to integrate with the 
    change control process;
If these requirements have already been documented (for previous projects or as a corporate 
standard) then they should be reviewed/confirmed with the relevant asset management 
“clients”. If not, the clients” should be identified and their requirements documented.

Asset Management Scope

Although project asset in principal can be very varied. In practice, the scope is often restricted to 
physical and non-physical items such as software and documentation.

Examples of deliverables which may be subject to asset 

management are:

  • User requirements documentation, scoping documents;
  • Functional specifications;
  • Acceptance test scripts/data,

Examples of non-deliverables which may be subject to asset management 

are:

  • Vendor proposals (may be required  for software selection projects);
  • User procedures;
  • Team training guides and manuals;
  • Operations documentation.
In order to facilitate the control of documentation, responsibility for the project library is often 
allocated to the asset manager. For project documentation, electronic copies should be controlled. 
Documentation produced by third-parties should be controlled through hard copies only.
In the case of functional and technical specifications, their relationship with software deliverables 
needs to be maintained. Hence, when a piece of software is changed, the relevant specifications 
must be kept in step.
Finally, the organisational scope of the asset management function needs to be defined. If the 
asset manager is given direct responsibility other functions, such as project change control, file 
backup and security, they need to plan how they will interface with these areas and ensure that all 
concerns are met.

Asset Management Plan Development

Asset Management Plan

The asset management plan is the key document produced by the asset management function 
outlining how this is to be implemented on the project. It should cover:
  • Asset management scope and objectives (with reference to documented requirements) 
    — most of this will have been identified in task “define asset management requirements 
    and scope”.
  • The project responsibilities of the asset management function and its organisational 
    structure;
  • Asset management (and other relevant project) procedures to be adopted, and tools to 
    be used, i.e. excel spreadsheet for library.
  • The approach to auditing compliance with procedures;
  • Asset management conventions to be used
    • Version controls
    • Naming conventions in compliance with project standards if already agreed
    • Filing systems for both physical and non-physical items
  • Security controls and procedures to be adhered to by project team members;
  • How project deliverables are to be classified. This will normally be in functional/ sub-system 
    groupings (e.g. General ledger, personnel sub-system) with a liaison representative or role 
    (with deputy) identified for each functional grouping. In addition deliverables will normally be 
    classified by deliverable type (e.g. Procedures documents) The approach to training project 
    members in procedures and, where necessary, the use of tools
  • Training should also include education about the need for, and benefits of, effective asset 
    management.
  • A asset management implementation plan with tasks, dates and responsibilities. This should 
    be included in the detailed work plan;    
  • A glossary of terms used; and
  • How asset management will integrate with other functions such as project change control.

Physical security of project area

Generally, the project team works within pre-established organisational security provisions and 
guidelines. However, both the project and asset manager should review the applicable guidelines to 
ensure:
  • Project team members have appropriate access privileges to all required areas;
  • Storage facilities for project documentation, project management files, and work in progress 
    are secure;
  • Project team members can obtain access during non-standard work periods for out of hours 
    testing, overtime work, and other valid reasons;    
  • Subcontractor personnel have appropriate access to files; and,
  • Disaster recovery procedures include at least the addition of the project manager’s name to 
    the emergency “call out list” in the event of a disaster.

Baseline Items

The process of taking a baseline (or snapshot) involves freezing the a deliverable at a moment in 
time. The baseline is normally the result of a particular milestone or a deliverable which is critical to 
the project meeting the agreed approvals.
All baselines should be retained for the entire life of the project.

Version control procedures

All project documents and deliverables must be subject to version controls. This ties in with the 
baseline of items and managing change on project deliverables.
In a standard version control system there are two stages:
  • Draft;
  • Approved,
The control of version is managed through a simple numbering system. If there is a point before the 
number then the version is in draft, if there is a zero after the point then this indicates that the item 
has been subject to agreed approvals and authorisation has been given to issue the approved
version. The highest version with a zero after it is the latest version, although a more recent daft 
maybe in distribution.
The figure below displays version 2.0 as the latest approved version, however the most recent 
document is draft 2.1

Figure 1.
                         0.1, 0.2, 0.3 … 0.n
DRAFT                    1.1, 1.2, 1.3 … 1.n
                                        2.1

APPROVED            1.0
                            2.0

Asset Management Process

Implementation and Administration

The Project Manager is responsible for allocating ownership for the implementation and continued 
administration of the asset management plan. This includes the coordinating of all team training on 
procedures and tools. They will also be responsible for updating procedures as needed throughout 
the project.
Ongoing asset management addresses the control and management of deliverable and 
non-deliverable assets. Work in progress is not affected (except for periodic backups).

Asset Control Library

The simplest mechanism for control is developing an Asset Library which will log and control both 
physical and non physical project assets. Procedures set out in the asset management plan can then 
be implemented to support the control of the defined assets.
The table below defines the minimum, requirements for the project asset library control log to ensure
effective administration.

Asset Control
Description
Asset ID   
Unique sequential asset identifier associated with asset organisation.
Asset Name/Title
Name of the asset conforming to the naming conventions as set out in the 
asset management plan
Asset Type
Type of asset i.e. Hardware, Software, Document, Contract, Report, Plan, 
File etc
Description
Brief description of the asset
Deliverable
Indicate if the asset is a project deliverable or non-deliverable
Status
Indicate the current status of the asset, i.e. Expired,   Cancelled, In 
development, Awaiting Approval, Approved, or N/A in the case of physical assets 
such as  hardware
Version
       
Detail the version of the asset
Workstream
       
The Workstream where the associated liaison has been allocated. This will 
normally be related to the client classification in the asset definition
Owner   
The person responsible for the asset or the assets delivery
Date Out   
The date the asset was taken out of the library
Out With
The person who checked the asset out of the library
Date In
The date the asset was returned to the library to confirm it’s return
File Location
Either the physical or non-physical location where the asset is stored        

Control Reports

Reporting requirements vary and depend to some degree on the asset management scope. 
However, asset management systems should be able to produce the following types of reports:
List and status of all asset items, including:
  • version;
  • date of last update;    
  • name of person last updating; and,
  • history.
List of all asset items “checked out” of the system
  • item identification;    
  • name of person who has the item; and,
  • date item checked out.
  • Exception reports, such as items checked out for more than 30 days; and,
  • Ad hoc reports.
Audits should be conducted on a regular basis, such as quarterly. Audits should be used as 
follows:
  • Comparison between hard copies of documents and the electronic copies;
  • Ensure all logs are accurately maintained and the detailed documentation reflects what 
    is recorded on the logs;
  • Comparison between logs and physical project property;
  • Procedure audit; and,
  • Timeliness audits:
  • how efficiently are requests for asset items processed?
  • how quickly are completed items added to the asset control log?

Archive Project Assets

Project assets should be archived at the agreed upon time, and represent the condition the 
deliverable, non-deliverable asset at the time of delivery.

No comments :

Post a Comment