Review / Confirm Terms of Reference (TOR), Scope, Objectives
DEFINITION
The project requires a clear definition of its terms of
reference (ToR), scope and objectives.
This is a mandate to operate within the Customer organisation. It allows work to be correctly focused, and
the outcome to be measured against the original goals.
SUMMARY
The project manager should review the project proposal and
other relevant documentation to produce a preliminary statement of project ToR,
scope and objectives. He then needs to
assemble a core management planning team whose first task will be to validate
this document by conducting interviews and workshops with key personnel. A formal Project Constitution should then be
produced and agreed with the project sponsor.
PATH PLANNING GUIDANCE
This process is mandatory.
DEPENDENCIES
Prerequisites (Finish-Finish):
- (none)
- Review / confirm business needs and anticipated benefits (L020)
Dependent procedures (Finish-Start):
- Select Path(s) (L030)
- Define and agree project management techniques (L040)
RECEIVABLES
- Project Proposal
- Other relevant documentation (see “DETAILED DESCRIPTIONS OF TASKS” below), eg any existing Feasibility Study, Benefit Model or Cost/Benefit Analysis etc.
DELIVERABLES
- Project Constitution
TOOLS
- Project Management Methodology and Tools
DETAILED DESCRIPTION OF TASKS
Introduction
A clear definition of the project’s ToR, scope and
objectives is needed at outset to:
- to reduce the risk of gradual "scope creep";
- establish the assumptions upon which the project will be planned and executed; and,
- define a foundation for developing the remainder of the management plan.
The document produced at the conclusion of this process (the
Project Constitution) defines the mission to be accomplished by the
project. The mission may be refined in
subsequent steps, at the discretion of the sponsor and steering committee as
more information becomes available.
It is essential that the ToR, scope and objectives are
defined, documented and agreed. To that
extent this process is mandatory. The precise
techniques to be used and contents of the documentation may vary according to
circumstances. The remainder of this
process describes a recommended but optional approach.
Review existing documentation
The project manager should review existing documentation to
gain an understanding of the project background and history. Relevant documentation may include, but is
not limited to:
- project proposal;
- documentation produced during Project Initiation Phase
- project description and cost/benefit analysis;
- request for proposal (RFP); request for information (RFI); request for quote (RFQ) or equivalent documents;
- pre-proposal survey and interview notes;
- business plans;
- corporate information technology plan;
- organisation charts; and,
- existing functional and/or system documentation.
The strategic objectives of the project should be described
in one of the documents. If these
objectives are not defined, the sponsor and project manager should identify
specific users to research and document the project's strategic objectives.
During the review process, the project manager should
identify and evaluate:
- implied commitments and concessions that have not been formalised or clearly documented;
- constraints;
- unclear and/or undocumented anticipated benefits of the project;
- initial cost, resource or schedule estimates that appear to be unsubstantiated or potentially unrealistic; and,
- “overkill” - the possibility that the anticipated benefits could be achieved through simpler measures which may cost significantly less than current projections.
The project manager should prepare a preliminary document
summarising the key information from the documentation reviewed. The summary should include:
- the project’s objectives and scope;
- initial cost/benefit analysis;
- a list of topics requiring further information;
- missing information or documentation;
- constraints; and,
- risks.
Assemble a management planning team
The sponsor and project manager should identify a core
management planning team, whose first deliverable will be the Project
Constitution, but who will then assist with subsequent management planning tasks.
Team members should be knowledgeable about the subject matter and
generally include:
- the project manager;
- key functional personnel
- key technical personnel
- Specialists in the Application Modules
The core team is generally a small number of people, but the
scope of the project will dictate the team size. Additional resources may be called upon to
provide input as needed. For a large
project, developing the management plan may take considerable time and
commitment. Resources assigned to the
core team may need to be relieved of their daily responsibilities to ensure the
commitment is met.
The project manager should share background information and
documentation with the team and should obtain their input on the preliminary
document described in the preceding step.
Conduct interviews and workshops
The core team should review the preliminary document
produced by the project manager and then determine the best method of verifying
its content, and obtaining additional or missing information. The objective of verification, and gathering
additional or missing information is to refine or define in further detail:
- the objectives and scope of the project, what the project includes and what is excluded;
- assumptions to be used in the development of the management plan;
- needs of the organisation as they relate to the project;
- constraints such as time, cost or implementation schedule;
- risks associated with the project and the degree of severity;
- criticality of the project in relation to corporate objectives;
- commitment from senior management to support the project actively;
- management’s expectations and tolerance levels pertaining to costs and schedules;
- a description of the major deliverables and measurable success criteria;
- an assessment of the organisation’s readiness to undertake the project;
- geographic location requirements or constraints for the project team; and,
- potential staffing, logistical or communication constraints.
Individuals who are best suited to provide input should be
identified, such as:
- potential project sponsors;
- company directors and key functional managers;
- information technology management;
- end users;
- members of the committee or group who requested the project;
- members of the committee or group who authorised the project.
Appropriate methods for gathering the information depend on
the individuals involved. The core team
should be aware that opposing views may be presented and discussed. Individual interviews may result in the core team
having to reconcile differences through subsequent meetings. For this reason, facilitated workshops are
often the easiest and fastest method to gather necessary information.
A considerable amount of information can be gathered in the
interview and workshop process. Not all
of the information will relate to the project’s ToR, scope and objectives but
the core team should document the information for use in subsequent steps.
Produce Project Constitution and obtain approval from sponsor
The core team should prepare a formal document - the Project
Constitution - defining the project’s scope, terms of reference and
objectives. The project boundaries
defined here become the litmus test for what is and what is not part of the
project. These boundaries are the
foundation of the management plan document and become the basis for the
subsequent steps.
The boundaries may change as the project is defined in more
detail - for example, they may shift as the requirements are further defined
and broken down. Once the detailed
requirements have been approved, however, the boundaries should become firm.
The core team should discuss the document with the sponsor
and obtain approval. No further
management planning should take place until approval from the sponsor has been
obtained.
No comments:
Post a Comment