Thursday, January 14, 2016

Application Software Implementation - Selection Processes

Processes descriptions are numbered for ease of access.  These numbers do not necessarily represent the sequence in which they are performed.  Also for ease of access the numbers are prefixed by a letter showing the type of segment or path that it applies to. Below is a list of typical Launch Processes 




L
Launch (Project Launch & Segment Launch)
R
Requirements
S
Selection
D
Delivery
P
Post-implementation (Post-implementation Management, Post‑implementation review, Business Benefits Assessment)
Q
Quality Audit reviews
T
Terminate Project


Ref
Process
Path Templates
S010
Market Review
Selection - Full, Selection - Short Form, Selection - Hardware
S020
Advertise
Selection - Full
S030
Establish “Long List”
Selection - Full, Selection - Short Form, Selection - Hardware
S040
Format Requirements Matrix
Selection - Full, Selection - Confirm, Selection - Short Form
S045
Format Requirements Matrix (Hardware Selection)
Selection - Hardware
S050
Design, issue and agree pre-qualification criteria and invitation
Selection - Full, Selection - Short Form, Selection - Hardware
S060
Define and agree selection scoring scheme
Selection - Full
S070
Prioritise Requirements Matrix by criticality
Selection - Full, Selection - Confirm, Selection - Short Form, Selection - Hardware
S080
Prepare, review, agree and issue Invitation to Tender
Selection - Full, Selection - Short Form, Selection - Hardware
S090
Prioritise Requirements Matrix by weights
Selection - Full
S100
Automatic weighting
Selection - Short Form, Selection - Hardware
S110
Short List for ITT
Selection - Full, Selection - Short Form
S170
Vendor Conference
Selection - Full
S180
Package Fit Study
Selection - Full
S190
Mark Responses
Selection - Full, Selection - Short Form, Selection - Hardware
S200
Identify Issues
Selection - Full
S210
Confer with Vendors
Selection - Full, Selection - Short Form, Selection - Hardware
S220
Consult with reference users
Selection - Full, Selection - Short Form, Selection - Hardware
S230
Agree final marks and issues
Selection - Full
S240
Benchmark
Selection - Full, Selection - Confirm
S250
Prepare and agree selection report
Selection - Full, Selection - Confirm, Selection - Hardware
S300
Negotiate terms with vendor(s)
Selection - Full, Selection - Confirm, Selection - Hardware
S310
Prepare and agree contract(s)
Selection - Full, Selection - Confirm, Selection - Short Form, Requirements / Selection Fast Track, Selection - Hardware
S400
Feasibility prototype
Selection - Full, Selection - Confirm
S500
Interview client / customise requirements matrix
Requirements/Selection Fast Track
S510
Assess potential vendors
Requirements/Selection Fast Track
S520
Get vendors to respond to Requirements Matrices
Requirements/Selection Fast Track
S530
Evaluate responses
Requirements/Selection Fast Track
S540
Confer with vendors
Requirements/Selection Fast Track
S550
Confer with reference users
Requirements/Selection Fast Track
S560
Identify and agree preferred vendor
Requirements/Selection Fast Track
S600
Check business critical requirements against package
Selection - Confirm
S610
Prepare, issue and agree selection validation report
Selection - Confirm
S700
Implementation Strategy and Architecture
Selection - Full, Project Model
S710
Define Implementation Strategy
Selection - Short Form, Selection - Confirm, Selection - Hardware, Requirements / Selection Fast Track
S900
Update project materials
Selection - Short Form, Selection - Full, Selection - Hardware


No comments :

Post a Comment